Piping Engineering Articles Is Blog To Share Basic Piping Information And Piping Field Material.
Showing posts with label Piping Layout. Show all posts
Showing posts with label Piping Layout. Show all posts
Thursday, 4 August 2016
Monday, 1 August 2016
Piping Layout: PipeRack Piping Arrangement Drawing Part-1
The piperack general arrangement
is finalised during the development of overall plot plan. The exact width of
the piperack, numbers of levels and elevations, the access and maintenance
platforms are finalised during piperack piping study.
Normally, the piperack piping
study, with its structural and platform requirements is the first priority item
for detail engineering of a process unit. The piperack may be an integral part
of a process unit located in the middle of the unit or it may be an arterial part
connecting several services of other process unit.
The following data and drawings
are required to be studied before starting the detailed design of piperack
piping study:
Unit Plot Plan / Overall Plot
Plan, Piping and Instrumentation diagrams Plant layout specification, Client
specification, Material of construction, Fireproofing requirements
Wednesday, 27 July 2016
Piping Layout: TankFarm Piping And General Arrangement Drawing Part-2
PUMP LOCATION IN TANKFARM
To determiine the optimum location of pumps, the potential hazards and
client preferrence shall be considered.
Fig. illustrates the location of pump within the dyke area with the
curb wall height of approx. 400-500mm.
This design protects the pump from minor spillage within the dyke and
enable the discharge piping to exit the dyke over the wall and there is no need
to have dyke penetration seals.
The piping outside the dyke may run on a piperack or sleepers.The pumps
located outside the dyke area are illustrated in Fig.
Tank outlet piping can either penetrate the dyke or pass over the dyke in
case the minimum liquid level in the tank do cause cavitation in the pump.
Tuesday, 26 July 2016
Piping Layout: TankFarm Piping And General Arrangement Drawing Part-1
The study of the tankfarm consisting of a group of tanks shall be carried
out keeping the following basic points in consideration.
1. Grouping of tanks,
2. Specification of the content.
3. Capacity of tanks
4. Nature of hazard - fire
- toxic
- explosive
- corrosive
- bulk handling loading
5. unloading
6. Statutory distance
7. Requirement of Dykewall or curbing
8. Dykewall height or curb height calculation
9. Location of Pumps - inside dyke area
- outside dyke area
10. Approach to tank nozzles with valve
11. Approach to tank roof
12. Drainage of dyke area - Sump and pump
13. Road around tankfarm
14. Fire hydrant / monitor requirement
15. Underground system connected to specific system of treatment / disposal
Thursday, 15 October 2015
Piping Layout: Heat Exchanger And Condenser Location In Plant And Piping Arrangement
INTRODUCTION
Heat Exchangers are widely used equipments in the chemical, petrochemical and refinery type of plant. The control of heat within a plant
operation is done by direct heat application in
a furnace, or by heat exchange in a shell and tube exchanger / plate
heat exchanger. Types of heat exchanger may be Shell and Tube, Aircooled (Fin-Fan), Plate type or Coil type(spiral).
Various process duties of heat exchanger have an effect on the layout aspects viz.
a. Exchange of sensible heat between two process fluids.
b. Cooling with air or water.
c. Chilling with refrigerated liquid.
d. Heating with steam or hot water.
e. Condense by water or a cold process stream.
f. Vapourising by steam (e.g. column reboiler) or any
heat transfer liquid.
Fixed tube exchangers
are
used
when
the
temperature differences between shell side and tube side
fluid are small.
Floating head or U-type exchangers are used where there is a significant temperature
difference.
Kettle -type reboilers are used for evaporation
in case of
limiting
pressure drop, otherwise
vertical reboilers are used
for evaporation.
Plate heat exchangers
are generally
used in
low-pressure, low temperature
applications. The plate
exchanger occupies less space than shell and tube exchanger for
equivalent heat exchanger surface.
Aircoolers are
used for overhead
condensers of column
and consist of fin-tube bundles with a header
box to each end, having inlet on top of header-box
at one end and outlet on bottom
of header box at the other end.
For single pass arrangement of air-cooler
exchangers, inlet nozzles are mounted on the top of the header box
and the outlet nozzles are located at the opposite end and mounted on the bottom of the header box.For double pass arrangement, the
inlet and
outlet nozzles
are located
at the
same end.
LOCATION
Exchangers should be located
close to the
major equipment with which it is associated in PFD / P&ID. Reboilers are placed next to
their respective towers and condensers are placed over reflux drums. Exchangers between two distant pieces
of process equipment should be
placed at optimal points
in relationship to piperacks.
Most exchangers are to be located at grade
level with elevations to have a
clearance of 1m above Finished Ground Level (FGL). Elevated
exchangers may be necessary to fulfill the NPSH requirement of a downstream
centrifugal pump.
In case of large numbers
of heat exchangers,
they are grouped in one or more category
to save pipe work,
structural work, provision of lifting and maintenance facilities, platform requirement etc. Paired or
grouped exchnagers shall be
spaced to allow minimum 450mm preferrably 600mm between
the outside of adjacent channel or bonnet flanges to facilitate access to flange bolts during
maintenance. Adequate space shall be provided on
either side
of paired exchanger and
at both ends of grouped
exchanger for control and
operator access as illustrated.
Groups of exchangers should be generally
located by the alignment
of channel nozzles in a vertical plane so as to present
an aesthetic appearance.
The support saddle
with oblong holes for provision of thermal expansion are normally
located on the saddle farthest from the channel end but the final location depends on the plant layout and the stress analysis
of the connected piping.
Exchanger piping should be as direct and simple as possible
by considering alternatives such as arranging exchangers side by side / stacking them for reversing flows.
Exchangers are sometimes mounted on structures,
process columns and other equipment. Special arrangements for maintenance and tube cleaning should be provided in such cases.
ACCESS FOR OPERATION
& MAINTENANCE
Internals of heat exchanger require
periodic cleaning and repair. It is important that exchangers and the surrounding piping are arranged to facilitate
access to the internal parts.
Horizontal
clearance of at least 900mm should be left between exchangers flange to flange or exchanger flanges to piping. Where space is limited, clearance may be reduced between
alternate exchangers but in
no case clearance over insulation between
channel flanges shall be less
than 600mm.
The channel ends of exchangers
should face the local access road for tube bundle removal and the shell
cover should face the piperack. Pulled out bundles
should not extend over
main access road.
A typical
exchanger arrangement with clearance for
access, operation
and maintenance
is shown.
Access for tube bundle removal is usually 500mm more than the bundle length.
Mobile equipment should be used for handling
tube bundles and covers at grade level. Expensive
built-in facilities e.g. lifting
beams, monorails to be kept minimum.
Wednesday, 14 October 2015
Piping layout: Pump Piping And Location
The design of a piping system can have an important effect on the successful operation of a centrifugal
pump. Such items as sump design, suction piping design, suction and discharge pipe size and pipe supports must all be carefully considered. A typical horizontal centrifugal pump installation is illustrated.
Selection of the discharge
pipe size is primarily a matter of economics. The cost of various pipe sizes must be compared to the pump size and power cost required to overcome the resulting friction head.
Monday, 12 October 2015
Piping Layout: Compressor Piping And General Arrangement Drawing
Compressors are normally
located inside a permanent shelter or building (Compressor House) for weather
protection. The compressor house can be fully covered by side cladding to grade
level if handling non-hazardous materials e.g. air.
For compressor, handling
flammable materials, ventilation and weather protection is assured by significant openings upto 2.5m ht. at grade level
together with roof ventilators.
Except for lighter than air
gases, trenches, pits and similar gas traps should be avoided within gas Compressor House. This will eliminate chances of suffocation or explosion risk due to accumulation of heavy
gases in pits.
For open compressor house, the side cladding on
all sides should be provided upto 1m below crane level.
The general arrangement of compressor house shall consider
the vendor drawings
and vendor recommendation, if any, for space and location of auxiliary units.
For compressor house where a
number of installations from multiple vendors are to be accommodated,
a thorough discussion should be held among the engineers of Piping, Process and Civil discipline to finalize the detail plot plan
of the unit.
The clear space between compressors shall be minimum 1.5m or half width of the compressors. The clearance between
rows of compressor and at the end of each compressor shall be also 1.5m.Built-in maintenance equipment viz. travelling
gantry with overhead crane / monorail with hoist and chain-pulley blocks
as well as the drop-out
areas shall be provided in the compressor house.
Piping Layout: Drums And Vessel Layout Nozzle Orientation And Platform
The process vessels and drums
are cylindrical hollow vessels used in process plants as intermediate
containers. They are often used to provide surge volumes for liquid-vapour separations
on distillation columns or separating mixtures of immiscible liquids. Other uses are flash drums, condensate and other process liquid collectors and holding drums for additives
and chemicals.
The piping study
on drums shall consider the general requirements for drum plant
layout and provide information
required to locate nozzles, instruments, piping and controls for plat forming and operation / maintenance access.
In the first study of plot plan, platform
levels and details of vessel elevations are set from process requirements (net positive suction
head - NPSH, gravity feed,
barometric legs etc.) and from considerations of access for safe and convenient
operation and maintenance.
Methods of supporting vessels
and operating platforms are detailed. Access for lifting equipment or overhead hoists and trolley beams is arranged for removal of
motors, mixers and internal heat exchangers from
process vessels. A platform should always be
provided for the removal of such heavy items of equipment and for access to manholes, sight glass, light
glass etc.
Subscribe to:
Posts (Atom)